Whiskey Creek owners seek answers after years of delays
Three property owners sought answers about construction delays. Officials maintain the county isn't stopping the work.
11:43 p.m. Nov. 16, 2026
A bridge to nowhere? The privately owned bridge into The Retreat at Whiskey Creek remains at the center of a dispute over construction access. Property owners say they cannot get the equipment needed to finish their homes onto the site, while Moore County officials insist they have not stopped construction.
DUANE CROSS
MCO Publisher•Editor
Carol Morris has more than $100,000 invested in property at The Retreat at Whiskey Creek. Five years later, she is still paying taxes on land she says she andd her husband, John, cannot use as planned.
"We're sitting on land that's worthless, basically," Morris told the Metro Council on Monday night.
Morris joined fellow property owners Guillermo Vulcano and Stephen Jernigan at the Nov. 16 meeting, seeking answers about the stalled vacation-home development and the long-running disputes between developer Chip Hayes and county officials. The owners say construction remains stalled. County officials insist nothing is preventing the work from moving forward.
If the county isn't stopping construction, why can't the owners finish their homes?
Permission doesn't guarantee access
Vulcano told council members he owns two lots with homes approximately 50% to 60% complete. Work has stopped, he said, and Hayes has explained that getting large construction equipment into the development remains a problem. Vulcano wanted to know whether that explanation matched the county's understanding of the situation.
The development's privately owned bridge has been a recurring point of contention. Morris said Hayes had obtained an engineering assessment of the bridge, but county officials had not accepted it. She questioned why the county had not completed a separate inspection.
Council members disputed the suggestion that county government was preventing construction.
"The county is not holding this project up one bit," said Dexter Golden, a District 3 council member and chair of the Moore County Planning and Zoning Commission.
Officials explained that the county's bridge concerns involve whether emergency vehicles can safely cross and whether the engineering documentation would satisfy insurance requirements. They maintained that those requirements do not prohibit construction equipment from entering the development. The county also has not agreed to pay for another bridge assessment, which officials said remains the developer's responsibility.
The distinction leaves a practical problem unresolved. Permission to build does not necessarily mean the machinery needed to finish construction can reach the property.
Council members acknowledged that one construction entrance had been considered unsafe for entry and exit. They also discussed a separate construction easement Hayes had previously arranged across private property behind the development. Officials said the easement existed early in the project but could not confirm whether it remains usable.
Any changes to that private arrangement, they maintained, were outside the county's control. The discussion did not establish which route is currently available for the equipment needed to finish the homes.
Questions about the original approval
Morris questioned how the development reached this point.
The project was approved for tiny homes, with individual lots sold to buyers who expected to build vacation properties. Yet years later, some owners are still waiting for the infrastructure and access needed to complete their plans.
Morris asked how the county could approve the division of the property into residential lots when construction access and emergency vehicle access would later become such significant concerns.
The Retreat at Whiskey Creek was originally approved under a special R-3 zoning classification rather than the county's conventional subdivision process. Golden explained that ordinary subdivision regulations included performance-bond provisions intended to provide financial assurances for required infrastructure, but the development had not been treated as a conventional subdivision.
The R-3 classification was subsequently removed from the county's zoning regulations. The council did not examine the original approval documents Monday, leaving unanswered what protections, if any, accompanied the approval and sale of the lots.
Officials maintained that the county provides the public road leading to the development's bridge, while responsibility for roads and utilities within the property rests with Hayes and the private property owners.
They also reiterated that the county has not issued a blanket prohibition against Phase 1 construction. The council has required that phase to reach 75% completion of its water and electrical infrastructure before considering Phase 2, but officials said that requirement does not prevent work already approved from continuing.
A separate dispute involving the permitted square footage of an individual home also was discussed. Council members said it affected one building permit, not construction throughout the development.
Waterlines scheduled for testing
Metro Utility Department Manager Ronnie Cunningham offered an update that could signal progress.
Cunningham said crews expect to test waterlines at The Retreat at Whiskey Creek on Wednesday, Nov. 18, checking for leaks before the system can be placed into service. Water and sewer infrastructure has been installed in portions of the development, he said, although he could not confirm how much of the overall project was complete.
The testing does not mean regular water service will immediately be available throughout the development. No timetable was provided for finishing the remaining utility work.
For owners who have already waited years, the update offered some encouragement but little certainty about when their homes could be finished.
Caught between competing accounts
Morris made clear that she wasn't there simply to blame Hayes. "I don't believe that it's all Chip's fault, honestly," she said.
She described a frustrating pattern in which the developer and county officials offer different explanations for the delays, leaving property owners unsure whom to believe.
The owners want the development finished so they can enjoy their properties and rent their homes to visitors. Morris said she also wants Lynchburg to benefit from the additional tourism spending.
"We want to rent these things, and we want people to stay overnight in Lynchburg and enjoy themselves," she said. "We're just wondering, what do we do at this point?"
Golden said the county wants The Retreat at Whiskey Creek to succeed, and maintained that the county has not prevented Hayes from completing Phase 1 and that responsibility for the remaining construction rests with the developer.
After the meeting, Golden, District 4 council member Peggy Sue Blackburn, and District 5 council member Brandon Ross spent additional time with the property owners, listening to their concerns.
Hayes was absent from Monday's discussion, although Golden said he had contacted the developer the previous week about providing an update.
Reached by the Observer after the meeting, Hayes said he missed the session because he mistakenly believed the council was meeting Tuesday. Hayes ended the conversation to take another call. The Observer did not obtain his response to the property owners' concerns about construction access.
The council announced no agreement on construction access or a completion date. For the owners, the practical question remains: Which route can accommodate the equipment needed to finish their homes?
More MUD

BZA leaves Whiskey Creek RV park unresolved
Road access, bridge concerns took center stage as proposed 45-space RV park stalled before the Board of Zoning Appeals.

Four years in, Whiskey Creek remains unfinished
79-lot tiny-home development remains unfinished as developer, Moore County work through access, bridge, zoning issues.

Who controls the Retreats? Model is under pressure
Lawsuits at Water’s Edge, Sunset Bluff testing HOA control, rental restrictions, finances, behind Chip Hayes’ communities.